DHL Express, Brisbane Airport

Completion date

2018

Client

BAC

Location

Brisbane Airport

Program

30 weeks

Our award of this Design & Construct project resulted from a full tender process and was celebrated as a continuation to the relationship we have enjoyed with BAC.With the base building project scope involving a partial demolition of an adjacent building (occupied by DHL) to accommodate the full new site footprint and considerable bulk excavation of unsuitable material the team wanted to get out of the ground as quickly as possible to mitigate wet weather delays.

This new DHL Express Gateway & Service Centre comprises 3,500m2 of warehouse, 780m2 offices, 2,650m2 heavy duty external paving, stand alone power generation systems and state of the art services and management systems.

The ultimate success of this seven month long project was due to the close collaboration and coordination with BAC, DHL & Gaskin Construction Services.

Related projects